39th Street & Fontenelle Street Sewer Separation Project

Completed Date

November 2015

Cost at Completion

$1,265,740

Project Location

39th Street at Fontenelle Street

Project Description

The 39th Street and Fontenelle Street Sewer Separation Project will reduce or eliminate the frequency of sewer backups in the project area.  The project includes construction of approximately 2,000 feet of new sanitary sewer.  Approximately half of this alignment was installed using trenchless or tunneled construction.  In addition to the sewer separation work, new pavement was installed on 39th Circle and partial driveway replacements will occur in much of the project area.  Periodic minor traffic disruption, specifically lane closures, on Sorensen Parkway and Fontenelle Boulevard occured during construction.

Project References

Project Number: OPW 51817