Omaha CSO

Skip to content

Burt-Izard Lift Station Improvements

The existing Burt-Izard Lift Station was originally constructed in the 1960s and initially had a capacity to pump 50 million gallons per day during wet weather events. However, because of significant grit loadings to the facility, the condition of the South Interceptor Force Main, and the historical lack of treatment capacity at the Missouri River Water Resource Recovery Facility (MRWRRF), the facility only operated at 25 million gallons per day during wet weather events.

The lift station improvements included upgrades to the grit building and overall grit handlings capacity, bar screen room and lift station. The improvements required upgrades to the electrical, structural, architectural, instrumentation, heating, ventilation, air conditioning and process elements of the facility to meet new code requirements and for operations and maintenance of the upgraded facility. The improved facility restored the firm capacity of the facility to pump 50 million gallons per day into the new South Interceptor Force Main for subsequent treatment at the expanded and upgraded MRWRRF.

Additional Resources

Project Map: Burt-Izard Lift Station Improvements

factsheet.png   Project Factsheet

roadconditions.png   Road Conditions

Schedule

Start-up activities will continue through Q1 2022. The South Interceptor Force Main–North Segment was placed into operation in Q3 2021 as part of the start-up activities.


Contact Information

City of Omaha
Jake Hansen
444-3922, Ext. 2202

Consultant/Contractor
CDM Smith
Amy Kliewer
816-412-3179

Public Facilitator
Emspace + Lovgren
Brian Kaminski
402-964-0213
brian@emspacegroup.com


Project References

Project Number:  OPW 52472

LTCP Project Name:  Burt-Izard Lift Station