Omaha CSO

Skip to content
Saddle Creek Retention Treatment Basin Project

Saddle Creek Retention Treatment Basin

 
 
 
Video Thumbnail
 
 
 
 
 
 
 
 
 
 
1:30
 
 
 
 
 
 
 
 

This time lapse video illustrates construction progress at the Saddle Creek Retention Treatment Basin Project from June 2019 through mid-March 2021. Construction through summer 2021 will focus on completing exterior basin walls, interior walls and columns.

The purpose of the Retention Treatment Basin (RTB) is to capture combined sewage and store or  treat it during wet weather events. Combined sewage will be diverted from the Saddle Creek Sewer and conveyed to the RTB headworks, where large materials like cans, rocks, tree branches and floatable solids are removed using a grit pit and mechanical screens. Directly following screening, a disinfectant is added to the combined sewage flows to kill or inactivate pathogenic bacteria. For small wet weather events, the combined sewage will be fully captured (retained) in the underground basin.  For larger events, the underground basin will completely fill up and then a dechlorination agent is added just prior to flows discharging through an overflow channel to the creek.

The RTB will use dewatering pumps to empty the facility after a wet weather event has ended. These pumps will convey captured combined sewage volume into the downstream Papillion Creek Interceptor sewer for treatment at the Papillion Creek Water Resource Recovery Facility (PCWRRF).

Above ground improvements include a building to house controls, grit and screening equipment, and chemicals.  The building will provide office space for full-time operations staff, some additional city offices and maintenance for the facility.

An odor control system will be installed to address the risk of odors from the facility. The site will include fencing and lighting for security purposes. Deliveries will occur regularly but are not expected outside of typical business hours.

Over 190,000 tons of soil have been excavated for the construction of the 3.3 million gallon below-ground basin. Once completed, the RTB will capture and treat a combined sewage flow rate of up to 160 million gallons per day. Steel beams have been driven into the soils below the concrete basin to support the facility’s structure. These 848 steel beams (approximately 13 miles in total) support the weight of concrete, water, soil and other building materials. While 90 percent of the pile driving was completed by May 2020 for the underground basin, additional deep foundation supports will be installed in January 2021 for the above-ground operations and chemical buildings.

The concrete work for the first phase of the channel and diversion structure was completed in early 2020.

Construction from summer 2020 to fall 2021 will focus on placing rebar and concrete pours for the basin. Approximately 25,000 cubic yards of concrete, roughly 2,500 truckloads, will be used to construct the basin and the facility’s walls.

factsheet.png   Project Factsheet

roadconditions.png   Road Conditions

videos icon Program & Project Videos

Schedule

Basin roof construction continues. Chemical building construction has commenced on the west side of the site.

  • Operations Building – Summer 2021
  • Chemical Building – Summer 2021
  • Substantial Completion – Winter 2023
  • Final Completion – Summer 2023

Completed Date

Early Soils Removal – Q3 2016

Cost at completion

Early Soils Removal – $2.2 million


Contact Information

Construction Contractor
Hawkins Construction Company

Chris Grojean
Vice President
cgrojean@hawkins1.com
402-231-7811

David Langenberg
Vice President
dlangenberg@hawkins1.com
402-221-7602

Consultant
Stephen D’Alecy
Construction Manager
Wade Trim
sdalecy@wadetrim.com
402-885-7675

Public Facilitator
Emspace + Lovgren
Brian Kaminski
402-964-0213
brian@emspacegroup.com

City Project Manager
Jake Hansen
Omaha Public Works Department
jake.hansen@cityofomaha.org
402-444-5107


PROJECT REFERENCES

Project Number: OPW 52049
LTCP Project Name: Saddle Creek CSO 205 – 64th & Dupont RTB

Project Number: OPW 52049A
LTCP Project Name: Saddle Creek Retention Treatment Basin